  • Ticket #4431

    • Property Summary changed from Documentation for QA for testing to QA for External Testing
    • Property Sprint changed from 2011-05-05 (11) to 2011-05-19 (12)
  • Ticket #4431 – Description

    v24 v25  
    77Updated: The document is correct as of 31st of March and contains 12 external contacts. A draft email will be composed ready to be sent out.  
    88 
    9 A selected few from this list will be used to ask for external testing. The previsional date set when the external testing will begin shall be towards the end of May providing that all goes as expected with the internal testing.  
    10 There is no dependency/expectancy  
     9A selected few from this list will be used to ask for external testing. The previsional date set when the external testing will begin shall be towards the end of May providing that all goes as expected with the internal testing. The purpose of the external is purely to gain a broader test base where possible. The schedule gives the chosen external testers 3 weeks warning: 
     10 
     119th of May Email to be sent out - The email is now to be sent to ensure we are closer to the code freeze and internal testing.  
     12 
     1316th May Internal testing in Dundee starts - Allowing for a week for any major issues to arise from the internal testing. 
     14 
     1524th May - The initial proposed date for external testing to begin.  