Warning: Can't synchronize with repository "(default)" (/home/git/ome.git does not appear to be a Git repository.). Look in the Trac log for more information.
Notice: In order to edit this ticket you need to be either: a Product Owner, The owner or the reporter of the ticket, or, in case of a Task not yet assigned, a team_member"

Task #5652 (closed)

Opened 13 years ago

Closed 13 years ago

RFE: pre-import data & list specific images phase I

Reported by: jamoore Owned by: saloynton
Priority: major Milestone: Testing and Docs
Component: General Version: n.a.
Keywords: n.a. Cc:
Resources: n.a. Referenced By: n.a.
References: n.a. Remaining Time: 0.0d
Sprint: n.a.

Description (last modified by saloynton)

Probably one of the major time costs on the scenarios is getting the proper data (number of z/t/etc) available. Though it would reduce the number of permutations we tried, it might be nice to have some kind of setup (projects/datasets/etc) ready for initial testing.

The scenarios targeted in this cycle:

  • Scenario 16
  • Scenario 21.2
  • Scenario 21.3
  • Scenario 25
  • Scenario 28

The setup of this data is now being trialed with links between data of test images good and the new folder created of test_scenarios.
e.g. ln -s /ome/data_repo/test_images_good/..../ with /ome/data_repo/test_images_scenarios/scenario_1/

major time costs on the scenarios is getting the proper data (number of z/t/etc) available. Though it would reduce the number of permutations we tried, it might be nice to have some kind of setup (projects/datasets/etc) ready for initial testing.

Change History (21)

comment:1 Changed 13 years ago by saloynton

Can I arrange some time to review testing with you in terms of what worked and what didn't in Paris. I have a few initial ideas but this ticket would be included in my general review. I will also schedule a tuesday meeting after we get back from Paris to breakdown a few of the points so we can start with the changes in documentation and any additional things that will need to be put into place.

comment:2 Changed 13 years ago by jmoore

Sounds fine, Scott. I'm not sure what our commitments look like, but I'm sure we can find some time.

comment:3 Changed 13 years ago by saloynton

  • Milestone changed from OMERO-Beta4.3 to OMERO-Beta4.3.2
  • Priority changed from minor to major

comment:4 Changed 13 years ago by atarkowska

  • Milestone changed from OMERO-Beta4.3.2 to OMERO-Beta4.3.1
  • Sprint set to 2011-07-07 (1)

Referencing ticket #5992 has changed sprint.

comment:5 Changed 13 years ago by saloynton

  • Sprint 2011-07-07 (1) deleted

Referencing ticket #5992 has changed sprint.

comment:6 Changed 13 years ago by saloynton

  • Milestone changed from OMERO-Beta4.3.1 to Testing

comment:7 Changed 13 years ago by saloynton

  • Milestone changed from Testing to OMERO-Beta4.3.2
  • Remaining Time set to 2
  • Sprint set to 2011-07-21 (1)

comment:8 Changed 13 years ago by cxallan

  • Sprint changed from 2011-07-21 (1) to 2011-08-04 (2)

Moved from sprint 2011-07-21 (1)

comment:9 Changed 13 years ago by cxallan

  • Sprint 2011-08-04 (2) deleted

comment:10 Changed 13 years ago by saloynton

  • Description modified (diff)
  • Remaining Time changed from 2 to 0.75
  • Summary changed from RFE: pre-import data & list specific images to RFE: pre-import data & list specific images phase I

comment:11 Changed 13 years ago by saloynton

Referencing ticket #5992 has changed sprint.

comment:12 Changed 13 years ago by saloynton

  • Remaining Time changed from 0.75 to 0.25
  • Sprint set to 2011-08-18 (3)
  • Status changed from new to accepted

comment:13 Changed 13 years ago by saloynton

  • Owner saloynton deleted
  • Status changed from accepted to new

comment:14 Changed 13 years ago by saloynton

  • Owner set to saloynton

comment:15 Changed 13 years ago by saloynton

  • Status changed from new to accepted

comment:16 Changed 13 years ago by saloynton

  • Owner saloynton deleted
  • Status changed from accepted to new

comment:17 Changed 13 years ago by saloynton

  • Owner set to saloynton

comment:18 Changed 13 years ago by jburel

  • Sprint changed from 2011-08-18 (3) to 2011-09-01 (4)

Moved from sprint 2011-08-18 (3)

comment:19 Changed 13 years ago by saloynton

  • Description modified (diff)
  • Milestone changed from OMERO-Beta4.3.2 to Testing
  • Sprint 2011-09-01 (4) deleted

comment:20 Changed 13 years ago by saloynton

Ticket closed because of the changes to the earlier implementation of testing in the development process. The setup of the test ready data is being handled in ticket #7087.

comment:21 Changed 13 years ago by saloynton

  • Remaining Time changed from 0.25 to 0
  • Resolution set to fixed
  • Status changed from new to closed
Note: See TracTickets for help on using tickets. You may also have a look at Agilo extensions to the ticket.

1.3.13-PRO © 2008-2011 Agilo Software all rights reserved (this page was served in: 0.69439 sec.)

We're Hiring!